Engineers in a clean room laboratory

Built within a constrained footprint, the fab features extensive underground utility infrastructure and a highly prefabricated construction approach.

Rethinking conventional design approaches  

To successfully deliver the project within significant space constraints, Exyte had to rethink conventional design approaches. Rather than expanding outward, the solution was to build downwards, transforming a limitation into a defining feature of the project. Unlike most semiconductor facilities, where key support buildings such as the Central Utilities Building (CUB) are arranged around the main fab, the restricted footprint left no room for horizontal expansion. Exyte’s answer was to move the majority of the technical infrastructure underground. 
Exyte Project Director, Manuel Magg

Exyte Project Director, Manuel Magg

Parallel progress with offsite manufacturing  

Exyte utilized OSM heavily on this project as a strategic response to ensure faster delivery, while also addressing the spatial limitations. Entire sections of the fab’s internal infrastructure including chemical, gas, water, wastewater, and exhaust systems, were pre-assembled in neighboring Czech Republic by Exentec, an Exyte company. These systems were built into large, fully integrated modules, measuring approximately seven by three meters, before being transported to Dresden and lifted directly into place.  

“OSM allowed us to do the most complex installation work somewhere else,” explains Magg. “When the modules arrived on site, they could be installed very quickly, rather than assembled piece by piece in a very narrow building. This approach improved safety, schedule, and simplified logistics by reducing on-site risks and enabling parallel fabrication and installation.” 

Exyte Project Director Mark Britton in PPE equipment on-site

Assistant Project Director, Mark Britton

Taking OSM vertical  

Installation of a network of vertical shafts of approximately 45 meters high was required to distribute gases, chemicals, and utilities through the building. Installing these systems on-site would have involved lifting and welding pipes of up to one meter in diameter at height, significantly constraining access and slowing progress. Instead, Exyte engineered large vertical riser sections, measuring between 18 and 20 meters in height, as fully finished assemblies. These were lifted in from above through the open roof, fixed in place, and successively stacked within the shafts. “While this approach required additional upfront engineering, it reduced installation time and on-site congestion,” explains Britton.